Seymour Falls Dam Vancouver, British Columbia
CDN
30 Tie Down Anchors: 26 Strand, Wax Encapsulated
Extruded Strand
Owner: GVWD (Greated Vancouver Water District)
Engineers: Acres International Ltd.
Contractor: Peter Kiewit & Sons
|
| |
Little Quinnesel Falls Hydro Electric Plant Penstock,
Niagara Wisconsin
Epoxy Coated Flo-Fill-Bond Strand, 6 Tie
Down Anchors: 14 Strands, 5 Tie
Down Anchors: 19 Strands, 77 feet long
Owner: Consolidated Paper Inc., Niagara WI
Engineers: Harza Engineering
Contractor: Layne Christensen
|
 |
Tom Miller Dam, Texas USA
55 Tie Down Strand Anchors:18 Strands (in Dam) & Stitch
Anchors in Spillway: CTS/TITAN IBO™ 40/16
Owner: LCRA (Lower Colorado River Authority)
Engineer: Freese and Nichols
Contractor: Nicholson Construction |
 |
Seven Mile
Dam, BC Canada
57 Tie Down Strand Anchors: 92 Strands,
up to 415 ft long, Wax Encapsulated Extruded Strand, 2000 Ton
Restressing System for Future Load Monitoring
Owner & Engineer: BC
Hydro,
Contractor: Peter Kiewit & Sons |
| |
Stave Falls Dam, BC Canada
30 Tie Down Strand Anchors: 19 Strands,
90 ft, first CTS Dam Strand Anchors (1985)
Owner & Engineer: BC Hydro, Contractor: Beck Drilling
|
 |
Point du Bois Dam, Manitoba Canada
6 Tie Down Strand Anchors in Sluice Way: 12 Strands,
80 ft
Owner: Manitoba Hydro, Engineer: KGS Consultants
Contractor: Arneson Construction
|
 |
Point du Bois Dam Power House, Manitoba Canada
48 Tie Down Strand Anchors: 18 Strands,
105 ft, Restressable, Monitored with SMS Gauges and Load Cells
Owner: Manitoba Hydro, Engineer: KGS Consultants
Contractor: Underground Services
|
 |
Pardee Dam, California USA
Epoxy Coated Flo-Fill-Bond Strand 48 Tie
Down Anchors: 18 Epoxy Coated Strands plus DCP, 160ft,
Monitored with Load Cells
Owner: East Bat M.U.D., Engineer: Woodward Clyde
Consultants, Contractor: Malcolm Drilling Co. Inc
|
| |
Mamquam River Dam, Squamish, BC Canada
25 Tie Down Strand Anchors: 7 Strands
Engineer: KGS Consultants, Contractor: Peter Kiewit
Co.
|
|
Tolt River Dam Intake Tower, WA USA
Epoxy Coated Flo-Fill-Bond Strand 6 Tie
Down Anchors: 60 Strands, 300 ft, Monitored
with Load Cells
Owner: City of Seattle
Engineer: Woodward Clyde
Contractor: Layne Christensen
Co.
|
 |
Rapides des Quinze Dam, Quebec Canada
18 Anchors: 15 Strands
Owner: Quebec Hydro, Engineer: Lavalin Consultants
|
 |
Wirtz Dam, Marble Falls
Texas USA
Epoxy Coated Flo-Fill-Bond Strand, 78 Tie
Down Anchors: 27 Strands, 58-148 feet long
Owner: LCRA (Lower Colorado River Authority)
Engineer: Freese and Nichols
Contractor: Layne Christensen Co.
|
| |
East Side Reservoir Intake Tower, near Hemmet CA
28 Tie Back Anchors: 32 Strands, Restressable,
Monitored with Load Cells
Owner: Los Angeles Water District
Contractor: Avar Construction
|
| |
Hollingworth and Gartshore Dams, Ontario Canada
6 Tie Down Anchors: 11 & 24 Strands
Owner: Great Lakes Power, Contractor: Geo-Foundations
|
| |
Pine Falls Dam, Manitoba Canada
39 Tie Down Anchors: 5 Strands
Owner: Manitoba Hydro, Contractor: Geo-Foundations
|
 |
Keenleyside Dam, Britisch Columbia BC
14 Tie Down Anchors: 37 Strands Owner: Columbia Basin Trust BC,
Contractor:
Peter Kiewit Sons, Inc.
|
|
Projects
| Bridges | Retaining
Walls / Slope Stabilizations | Others
|