![]() |
|
|||||||||
Articles and
Publications
|
|
Post-Tensioned Hollow Composite Micropiles
Second International Workshop on Micropiles (1999 IWM) in Ube City,
Preface The Loma Prieta Earthquake in the San Francisco Bay area on October 17th 1989 and the Northridge Earthquake in Los Angeles on January 17th 1994, prompted a vast review of all bridges and freeway structures by the California State Highway Department (CALTRANS). It was found that with an inventory of 11,000 bridges, most require seismic upgrading. Seismic forces apply dynamic horizontal and vertical loads on structures. They generate eccentric bending moments in the foundations, resulting into twisting of the structure and opening of the joint between footing and ground. This opening of the joint can be eliminated or reduced by post-tensioning, (pre-compressing). The dynamic seismic shocks shall be resisted by the elastic (spring system) post-tensioned strand tendons, eliminating or minimizing uplift of the footing. Overview
Con-Tech Systems developed this method and tested the same with Caltrans. The challenge was to develop a top anchor head, which withstands stress reversals. The tie-down anchors also had to be prefabricated and shipped coiled for low headroom applications under bridges. Strand anchors are ideal to fit this envelope. This method was then used in a number of Caltrans bridge retrofit projects in the LA and San Francisco areas. The Method in more detail A 16"dia. pipe pile is driven through the overburden and socketed into the harder load bearing strata. The pipes are cleaned out to within 24" of the pile tip, a 6"dia. PVC pipe is centered inside the pipe and concreted in. This PVC pipe serves as a drill guide to drill a 5"dia. anchor hole to a specified depth. The double corrosion protected CTS tie-down strand anchor, with a bond length and a permanent unbonded length, is installed through the PVC pipe into the 5"dia. anchor hole and grouted. After the grout reaches sufficient strength, the anchor is tested, tensioned and locked off on top of the pipe pile or footing. The amount of lock-off force is governed by the allowable max. elastic movement during seismic occurrences. Another factor is the allowable additional load on the footing, which is introduced during post-tensioning of the tie-down anchor Problems experienced with this method During one of the retrofit projects, (the Interstate Highway I-80 Viaduct, El Cerrito SOH Bridge in the San Francisco Bay area) it was noticed that the driven pipe piles, which were load tested and accepted right after installation, started to fail (settle) during the testing of the strand anchors. The testing applied an external vertical load to the pile. It was discovered, that either the clean-out drilling operation inside the pipe pile or the drilling of the hole for the tie-down anchor disturbed the ground under the pipe pile tip and therefore reduced the piles load carrying capacity. The project was stopped and Caltrans, after reviewing the problem, ordered an extensive Pile Load Test Program Con-Tech Systems TITAN-MICROPILE proposal Caltrans asked for comparison tests using 62mm DSI bars, tested but not locked off, versus the conventional, as specified, pipe pile/strand anchor tie-down.
The First Caltrans Field Test See Pile Load Test Report, El Cerrito SOH, Bridge No.33-0051L, Bent 15W, Pile 3C, 3D, 3E and 3F, Albany, California, Prepared for Caltrans by Delta Geotechnical Services. Piles 3C, 3D, and 3F were supplied by Con-Tech Systems and Pile 3E was supplied by DSI.
Comments to the test result The Failure of Pile 3C was expected. Piles 3D, 3E and 3F passed. It is, however, very interesting to compare the results of these piles which passed the test. As shown in the report, our proposal using the composite TITAN bar with post-tensioned strands, in pile 3F, performed best; even being the shortest pile it showed the smallest amount of movement. The DSI pile 3E also passed. Pile 3D passed marginally in compression, primarily due to the additional external load introduced during pre-stressing of the tie-down anchor on top of the pipe pile. The distance between the test piles of only 3-0", less than 1.0 m, helped the test result of the center pile 3E (untensioned DSI bar), especially due to the injection grouting used during the TITAN pile installation and the consequently ground consolidation. The piles should have been placed at least 8 feet apart What did we learn out of these tests? In Pile 3F, the internal pre-stress force pre-compressed the TITAN-MICROPILE internally without reducing its external load capacity. This pile did not shorten or elongate any more elastically until the external test load exceeded the internal pre-stress load. Therefore, the footing will also not move until this load is reached, which can then be considered the Design Load. The TITAN-MICROPILE, compared to the DSI bar pile, had less movement and less deformation; even though it was 10 feet shorter and has only half the steel cross-section area. The TITAN pile is therefore much more economical Second Caltrans Field Test In California, contractors must conduct a pre-qualification MICROPILE Test Program in order to be able to tender on Caltrans projects.
A large California contractor, Malcolm Drilling Co., applied for their field test program. Knowing the many advantages of the TITAN-MICROPILE, they added this pile to the program. The test requirements are: Max. movement shall not exceed 0.500" @ 300 kips. Based on an old existing soils report, provided by Caltrans, MDC calculated the pile length for the composite casing pile at 60.0 and for the Injection Bore TITAN pile at 30.0. We supplied the following materials: TITAN 105/53 bars for 2 test piles, one tension pile and one compression pile, and TITAN 103/78 bars for the reaction piles. The test results for this test are most interesting.
This confirms that the friction values indicated in the TITAN-MICROPILE brochure are at least 2 x the values for the composite casing/bar piles. A new test had to be conducted at the same site with both pile systems lengthened by 30, because, as mentioned before, the soils report was very old and did not indicate the additional land fill, which occurred at a later date.
The load at Geo. Failure for both pile systems was around 600 kips, (300 T). The Test Report concludes the following:
| |||||||||||||||||||||||||